Question: Ettlie Engineering has a new catalyst injection system for your countertop production line. Your process engineering department has conducted experiments and determined that the mean

Ettlie Engineering has a new catalyst injection system for your countertop production line. Your process engineering department has conducted experiments and determined that the mean is 8.01 grams with a standard deviation of .03. Your specifications are: μ = 8.0 and σ = .04, which means an upper specification limit of 8.12 [ = 8.0 + 3(.04)] and a lower specification limit of 7.88 [= 8.0 - 3(.04)]. 

What is the Cpk performance of the injection system?