Question: Given below is the input part of an input/output control report a. Compute the cumulative deviations in input. b. What is the minimum queue this
Given below is the input part of an input/output control report

a. Compute the cumulative deviations in input.
b. What is the minimum queue this work center could start with and not run out of work?
c. How much capacity should the work center have on average to keep the average queue at this work center at its starting level?
Planned input 400 400 400 400 400 400 Actual input 317 416 420 331 489 316 Cumulative input deviation