Question: A brick seller's demand forecasts for the next 10 weeks are 25, 25, 25, 25, 20, 30, 30, 30, 25, and 30 units. The current

A brick seller's demand forecasts for the next 10 weeks are 25, 25, 25, 25, 20, 30, 30, 30, 25, and 30 units. The current on-hand inventory is 110 units. The order policy is to produce in lots of 70. The booked customer orders for the item, starting with week 1, are 12, 35, 5, 7, 5, 9, 3, 12, 0, 0, and 0 units. The lead time is 2 weeks.

a. Develop an MPS for the bricks.

b. The marketing department has received five orders for this item in the following sequence:

Order 1 is for 18 units to be delivered in period 1. Order 2 is for 70 units to be delivered in period 3.


Assuming that the prospective MPS you developed in part (a) does not change, which orders would you be able to accept based on the available to promise (ATP)?

Order 1 is for 18 units to be delivered in period 1. Order 2 is for 70 units to be delivered in period 3. Order 3 is for 85 units to be delivered in period 6. Order 4 is for 70 units to be delivered in period 7. Order 5 is for 85 units to be delivered in period 9.

Step by Step Solution

3.56 Rating (160 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Creating an MPS for bricks We must evaluate the demand forecast onhand inventory booked customer orders and order policy lots of 70 for this Well bu... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Operations Management Questions!