A production process is required to produce 1,400 of product X, 840 of product Y and 420

Question:

A production process is required to produce 1,400 of product X, 840 of product Y and 420 of product Z in a fourweek period. If the process works seven hours per day and five days per week, devise a mixed model schedule in terms of the number of each product required to be produced every hour that would satisfy demand.