A project consists of four tasks: A, B, C, and D. Task A must be completed before

Question:

A project consists of four tasks: A, B, C, and D. Task A must be completed before B and C are started, and task C must be completed before task D is started. Each task takes 1 day to complete. What is the duration of this project?