Question: An operations manager wants to balance a line as efficiently as possible. The desired daily output rate is 60 units, and the line operates 9

An operations manager wants to balance a line as efficiently as possible. The desired daily output rate is 60 units, and the line operates 9 hours a day. Given the precedence diagram, assign the tasks to workstations according to the following heuristics:

1. Most following tasks rule.

2. Ranked positional weight rule.

3. Compute the balance efficiency for both rules. Which assignment is better?

4 min 9 min 6 min 8 min 5 min A B 3 min 5 min 9 min 4 min

4 min 9 min 6 min 8 min 5 min A B 3 min 5 min 9 min 4 min

Step by Step Solution

3.24 Rating (173 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

1 Cycle time is 9 minutes A 8 B 5 D 3 C 3 F 2 E 2 H 1 G 1 I 0 Most following tasks rule CT 9 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Operations Management Questions!