Question: Complete the available-to-promise table below: On Hand = 30 Forecast Customer Orders Master Production Schedule Available-to-Promise 1 2 100 50 75 50 100 50 Period
Complete the available-to-promise table below:

On Hand = 30 Forecast Customer Orders Master Production Schedule Available-to-Promise 1 2 100 50 75 50 100 50 Period 3 100 4 50 116 73 50 100 5 100 45 100 6 50 23 50
Step by Step Solution
3.51 Rating (158 Votes )
There are 3 Steps involved in it
Answer Bs on Hand 10 Per iod 1 Per iod 2 Per iod 3 Per iod 4 Per ... View full answer