Question: Complete the MPS record shown in Figure 11.30 for a single item. Item: A Quantity on Hand: Forecast Customer orders (booked) Projected on-hand inventory MPS
Complete the MPS record shown in Figure 11.30 for a single item.
Item: A Quantity on Hand: Forecast Customer orders (booked) Projected on-hand inventory MPS quantity MPS start 75 1 65 January 2 65 40 10 3 4 65 45 85 5 50 Order Policy: 100 units Lead Time: 1 week February 6 50 35 70 7 50 8 50
Step by Step Solution
★★★★★
3.49 Rating (152 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Based on the image you sent heres how you can complete the MPS record for a single item Item A Order Policy 100 units Lead Time 1 week January Februar... View full answer