Question: Consider the data for a simple project at Carlos Lopezs real estate development company, as given in the following table. a) Note that this project

Consider the data for a simple project at Carlos Lopez’s real estate development company, as given in the following table.ACTIVITY Q R s T a 7 1 10 1 DAYS m


a) Note that this project has only one path. What is the expected completion time of the project?b) What is the probability of the project being completed within 38 days?

ACTIVITY Q R s T a 7 1 10 1 DAYS m 10 6 12 5 b 12 23 16 7 IMMEDIATE PREDECESSOR R S

Step by Step Solution

3.34 Rating (163 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a The expected completion time t is 983 800 1233 ... View full answer