Question: Consider the following project network, with task duration data provided: Please answer the following questions, based on your analysis of this diagram. a. What is

Consider the following project network, with task duration data provided:start A 1 C 2 B D 2 62 H 3 finish

Please answer the following questions, based on your analysis of this diagram.

a. What is the critical path through this network?

b. What is the completion time for this project?

c. What is the slack in activity A?

d. All tasks longer than 1 day can be crashed to as little as 1 day, although prices vary. Task B costs $600 per day to crash, while task H costs $200 per day, and all other eligible tasks cost $100 per day. Which tasks should be crashed to shorten this project to 8 days? How much will this cost?

start A 1 C 2 B D 2 62 H 3 finish

Step by Step Solution

3.41 Rating (148 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Sure lets go through each question a The critical path is the longest path through the network where ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Operations Management Questions!