Question: Courtney is a programmer receiving requests each week to analyze a large database. Five jobs were on her desk Monday morning, and she must decide

Courtney is a programmer receiving requests each week to analyze a large database. Five jobs were on her desk Monday morning, and she must decide in what order to write the code. Assume that all jobs arrived today (day 1 and hour 1) in the order shown below. Courtney has assigned the number of hours required to do the coding as noted. Note that Courtney works an 8-hour day and today is a workday.

JOB A B DE DUE DATE (HOURS HENCE) 8 16 24 32

a) Sequence the jobs according to EDD.
b) What is the average completion (flow) time?
c) What is the average job lateness?
d) What is the average number of jobs in the system?

JOB A B DE DUE DATE (HOURS HENCE) 8 16 24 32 12 DURATION (HOURS REQUIRED) 5 2 10 16 6

Step by Step Solution

3.41 Rating (167 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a EDD AEBCD b Average completion time 91 5 1820 hours c Aver... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Operations Management Questions!