Question: Dumfries Industries is generating a materials requirement plan for the next 6 weeks. Here is its most current information: a. How many levels does a
Dumfries Industries is generating a materials requirement plan for the next 6 weeks. Here is its most current information:
a. How many levels does a product structure for Dumfries' item A have?
b. Using MRP methodology, how much of parts A, B, and C should be ordered, and when should they be ordered?
c. Which item will experience the highest ending inventory, following this plan?
Master Production Schedule Week: 1 2 3 4 5 6 Item A 10 0 20 20 20 10 10 Other Information Item's Current Item Item's Parent Item's Lead Time Item's Lot Size On-Hand Inventory ABC None 1 week LFL 20 A 1 week 20 20 B 1 week 50 20
Step by Step Solution
There are 3 Steps involved in it
a The product structure for Dumfries Item A consists of two distinct levels when considering its components Item A itself is at the top level and its direct component Item B is at the next level Item ... View full answer