Question: In a two-bin inventory system, the demand for 3-inch lag bolts during the 2-week lead time is normally distributed, with an average of 53 units

In a two-bin inventory system, the demand for 3-inch lag bolts during the 2-week lead time is normally distributed, with an average of 53 units per week. The standard deviation of weekly demand is 5 units.
a. What is the probability of demand exceeding the reorder point when the normal level in the second bin is set at 130 units?
b. What is the probability of demand exceeding the 130 units in the second bin if it takes 3 weeks to receive a replenishment order?

Step by Step Solution

3.40 Rating (163 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Given that the average demand during the 2week lead time is 53 units per week and the standard dev... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Operations Management Questions!