Olympic Enterprises plans to assemble a new breed of mountain bikes as per the bill of materials

Question:

Olympic Enterprises plans to assemble a new breed of mountain bikes as per the bill of materials (BOM) in Figure 11.33.
a. Which component has more than one parent?
b. How many unique components does product A have at all levels?
c. How many intermediate items does product A have at all levels?
d. Given the lead times (LT) in weeks noted on Figure 11.33, how far can the business delay the purchase of component C if the outcome is beneficial for the business?

E (1) LT=2 B (1) LT=1 F (2) LT=3 (H (2) LT=3 E (1) LT=3 A LT=2 C (2) LT=4 G (3)) LT=2 1 (1) LT=1 (D (1) LT=2

Fantastic news! We've Found the answer you've been seeking!