Randas Commercial Bakery produces cupcakes to be sold in supermarkets in Egypt. The production line is available

Question:

Randas Commercial Bakery produces cupcakes to be sold in supermarkets in Egypt. The production line is available 12 hrs/day and is currently producing in large lots. The manager wants to reduce the production cycle to 4 hours. Given the data below, what is the setup time needed?

Annual Demand = 180,000 cupcakes
Number of working days per year = 250 days/year
Production capacity = 1,000 cupcakes/day
Holding cost = LE 40 per unit per year
Setup labor cost per hour = LE 20

How many minutes of setup time should she have her plant manager aim for regarding this component?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question
Question Posted: