Sitting on Maggie Klimchuks desk is the latest planned order report from the companys MRP system. Maggies

Question:

Sitting on Maggie Klimchuk€™s desk is the latest planned order report from the company€™s MRP system. Maggie€™s job is to determine if there is enough capacity to handle the workload and to level the load if it€™s uneven. She gathers the latest cost figures and gets to work. Subcontracting and hiring extra workers are not options at this point, but overtime, pulling work ahead, and postponing work are. Regular production costs $10 an hour and is limited to 40 hours a week. Overtime costs $15 an hour and cannot exceed 40 extra hours (i.e., a double shift). An inventory cost of $3 per period is assessed for each hour€™s worth of work performed in advance. Postponing work costs $20 per item per period.
Use the following information to construct an initial load summary chart. Level the loads. Then create a revised chart that meets demand at the least possible cost. How much money is saved by economically leveling the load?


Planned order report


Week 2 Item 90 250 100 600 160 D


Processing times


Setup Time (min) Run Time (min per unit) Item 15 3 30 15 50 10 IC 45 D

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management Creating Value Along the Supply Chain

ISBN: 978-1118301173

1st Canadian Edition

Authors: Roberta S. Russell, Bernard W. Taylor, Ignacio Castillo, Navneet Vidyarthi

Question Posted: