Question: Ten basic tasks must be performed on an assembly line to manufacture a product. The demand for the product is 60 units per day and

Ten basic tasks must be performed on an assembly line to manufacture a product. The demand for the product is 60 units per day and the line is available 8 hours per day. The time to perform each task and the immediate predecessors are shown below:

TASK A B D E F G H 1 J TASK TIME

a) Draw a precedence diagram of this operation.
b) Compute the cycle time for this operation.
c) What is the theoretical minimum number of workstations?
d) Assign tasks to workstations to minimize idle time.
e) What is the idle time of the process?
f) What is the efficiency of the assembly line, given your answer in (d)?

TASK A B D E F G H 1 J TASK TIME (MINUTES) 3 5 2 3 2 4 3 4 3 5 IMMEDIATE PREDECESSORS A A B, C E D, F G H

Step by Step Solution

3.45 Rating (155 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Answers a Precedence diagram A B D C E F G H I J b Cycle time 18 minutes c Theoretical minimum numbe... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Operations Management Questions!