Question: Using PERT, Jennifer Benson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and
Using PERT, Jennifer Benson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 4.
a) What is the probability that the project will be completed in 17 months?
b) What is the probability that the project will be completed in 20 months?
c) What is the probability that the project will be completed in 23 months?
d) What is the probability that the project will be completed in25 months?
e) What is the due date that yields a 95% chance of completion?
Step by Step Solution
3.56 Rating (170 Votes )
There are 3 Steps involved in it
a Probability of ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (2 attachments)
1496_60b7412250cca_647489.pdf
180 KBs PDF File
1496_60b7412250cca_647489.docx
120 KBs Word File