Question: Using PERT, Jennifer Benson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and

Using PERT, Jennifer Benson was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 4.
a) What is the probability that the project will be completed in 17 months?
b) What is the probability that the project will be completed in 20 months?
c) What is the probability that the project will be completed in 23 months?
d) What is the probability that the project will be completed in25 months? 
e) What is the due date that yields a 95% chance of completion?

Step by Step Solution

3.56 Rating (170 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Probability of ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (2 attachments)

PDF file Icon

1496_60b7412250cca_647489.pdf

180 KBs PDF File

Word file Icon

1496_60b7412250cca_647489.docx

120 KBs Word File

Students Have Also Explored These Related Operations Management Questions!