What is the relationship between the earliest start time (EST) of an activity and the earliest completion

Question:

What is the relationship between the earliest start time (EST) of an activity and the earliest completion time (ECT) of the activity? 

a. EST + Activity time = ECT 

b. EST × Activity time = ECT 

c. EST = ECT 

d. None of these statements is correct.