Question: Which method for project management method uses buffers? a) Program evaluation and review technique (PERT) b) Critical path method (CPM) c) Gantt chart d) Critical
Which method for project management method uses buffers?
a) Program evaluation and review technique (PERT)
b) Critical path method (CPM)
c) Gantt chart
d) Critical chain approach
Step by Step Solution
3.52 Rating (162 Votes )
There are 3 Steps involved in it
d Cri... View full answer