You need to schedule 10 units of product Alpha for delivery in 6 weeks. Three units of

Question:

You need to schedule 10 units of product Alpha for delivery in 6 weeks. Three units of D and 2 units of F are required for each Alpha. The lead time for Alpha is 1 week. Lead time for D is 1 week, and lead time for F is 2 weeks.
a) Construct a product structure.
b) Prepare a time-phased product structure.
c) Prepare a gross requirements plan for Alpha.