Question: 12. You are a project manager working on a large, complex project. You've constructed the WBS for this project, and all of the work package

12. You are a project manager working on a large, complex project.

You've constructed the WBS for this project, and all of the work package levels are subprojects of this project. You've requested that the subproject managers report to you in three weeks with their individual WBSs constructed. Which of the following statements are correct? (Choose three.)

A. The work package level is decomposed to create the activity list.

B. The work package level is the lowest level in the WBS and is known as a user story on an agile project.

C. The work package level facilitates resource assignments.

D. The work package level facilitates cost and time estimates.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!