Question: 18. A project has a tight budget when you begin negotiating with a seller for a piece of equipment. The seller has told you the

18. A project has a tight budget when you begin negotiating with a seller for a piece of equipment. The seller has told you the equipment price is fixed. Your manager has tol

A. Make a good faith effort to .find a way to decrease the cost.

B. Postpone negotiations until you ca.n convince your manager to change his mind.

C. Hold the negotiations, but only negotiate other aspects of the project.

D. Cancel the negotiations.