Question: 2. 1he customer has accepted the completed project scope. However, the le~sons learned required by the project management office have not been completed. What is
2. 1he customer has accepted the completed project scope. However, the le~sons learned required by the project management office have not been completed. What is the status of the project?
A. 111e project is incomplete because it needs to be replanned.
B. lhe project is incomplete until all project and product deliverables ,ue complete and accepted.
C. 111e project is complete because the customer has accepted the deliverables.
0. The project is complete bec,rnsc it h.1~ reached its due date.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts