Question: 25. A project manager is taking over a project from anothtr project manager during project planning. If the new project manager wants to see what

25. A project manager is taking over a project from anotht•r project manager during project planning. If the new project manager wants to see what the previous project manager planned for managing changes to the schedule, it would be best to look at the:

A. Communications management plan R Update management plan C. Staffing m;magcment plan D. Schedule management plan