25 You W<'rC just assigned to take ov...-r a project from .mother project nl

!he previous project manager tclb you that the project is on schedule, but only because he has const.mtly pushed the team to perform. What is the Jlrstthingyoushould do as the new project manager?

A. Check risk status.

B. Check cost perfom1ance.

C. Determine a management strategy.

D. Tell the team your o bj ective~.