Question: 29. During project executing, a team member is coordinating with a supplier, and identifies a risk that 1s not in the risk register. It appears

29. During project executing, a team member is coordinating with a supplier, and identifies a risk that 1s not in the risk register. It appears that the pieces ofheaq equipment you have ordered from a supplier are larger than anticipated, and they may not all fit into the warehouse the team has leased to store them until they arc needed. What should you do?

A. Get further information on how the team member identified the risk because you already performed a detail eel analysis and did not identify this risk.

B. Disregard the risk because risks were identified during project planning.

C. Inform the customer about the risk.

D. Analyze the risk.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!