Question: 30. You're thinking through what approach will make it easiest for the team to take responsibility for providing work performancc data for all aspects of

30. You're thinking through what approach will make it easiest for the team to take responsibility for providing work performancc data for all aspects of the project. As part of this appro.1ch1 yon b elieve it will be helpful to make sure the team understands how and why the data will be analyzed. You explain to the team that the cost management plan contains a description of:

A. The project costs B. How resources arc allocated C. The budget~ and how they were calculated n. llic vVBS level ,1t which earned value will be calculated