Question: 32. 1he project is calculated to be completed four days after the desired completion date. You do not have acce~s to addHional resources. The project
32. 1he project is calculated to be completed four days after the desired completion date. You do not have acce~s to addHional resources. The project is low risk, the benefit-cost ratio is expected to be 1.6, and the dependencies are preferential. Under these circumstances, what is the best thing to do?
A. Cut resources from an activity.
B. Make more act ivities concurrent.
C. Move resources from the preferential dependencies to the external dependencies.
D. Remove an act1vit}' from the project.