Question: 4. A detailed project schedule can be created only after cre.iting the: A. Project budget B. Work breakdown structur~ C. Project man.i.gement plan D. Detailed
4. A detailed project schedule can be created only after cre.iting the:
A. Project budget B. Work breakdown structur~
C. Project man.i.gement plan D. Detailed risk assessment