Question: 6. Your team is working on an agile project developing an app that alerts airline passengers to gate changes for their flights once they've checked

6. Your team is working on an agile project developing an app that alerts airline passengers to gate changes for their flights once they've checked in. They are having a difficult time understanding how the user stories work together toward the big picture. Which of the following should you do? (Choose two.)

A. Create a burndown chart.

B. Perform one-hour backlog refinement meetings midway through the upcoming iterations.

C. Tailor the approach to help team members gain a better understanding of the user stories.

D. Create an impact map.