Question: 8. When using an agile methodology to manage your project, all of the following Knowledge Areas have processes that are performed before, during, and after

8. When using an agile methodology to manage your project, all of the following Knowledge Areas have processes that are performed before, during, and after an iteration except for which one?

A. Risk Management B. Schedule Management C. Procurement Management D. Quality Management