Question: A new junior project manager seems to be having some difficulty understanding key terms used in the reports being prepared for the project. He is
A new junior project manager seems to be having some difficulty understanding key terms used in the reports being prepared for the project. He is particularly confused by the earned value management system and the approved project budget. You explain to him that there are easy ways to understand what each element means and demonstrate this by point out that the total planned value of the project is better known as what?
A: Approved project budget B: Cost baseline C: Actual cost D: Budget at completion