Question: A project is being done for an external customer. Which of the following is not an input to the Develop Project Charter process? A. Agreements
A project is being done for an external customer. Which of the following is not an input to the Develop Project Charter process?
A. Agreements B. Business Case C. Project Statement of Work D. Stakeholder register