Question: A project is contracted as a Time & Material (T&M) type of contract. The service provider initially estimates that the total effort involved would be


A project is contracted as a Time & Material (T&M) type of contract. The service provider initially estimates that the total effort involved would be about 1000 hours of effort. The project is contracted at a rate of US$ 75 per hour of effort. If the project ended up with 1200 hours of effort, what would the contract payout be.

A. US$ 75,000 B. US$ 90,000 C. US$ 82,500 D. US$ 120,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!