Question: A Project manager estimates the work to be accomplished in the near term in detail, at a low level of the Work Breakdown structure (WBS);


A Project manager estimates the work to be accomplished in the near term in detail, at a low level of the Work Breakdown structure (WBS); while he estimates work far in the future as WBS components, that are at a relatively high level of the WBS. What is this technique called?

A. Decomposition B. Rolling wave planning C. Scope Creep D. Earned value planning