Question: A project manager has just startedplanning his project. If he has very limited information about the project, he must use the following technique to estimate
A project manager has just startedplanning his project. If he has very limited information about the project, he must use the following technique to estimate the duration for each activity:
A. Four-point estimating B. Three-point estimating C. Analogous estimating D. Parametric estimating