Question: A project was awarded based on a competitive proposal. Management made a commitment that a few key team members would be made posted on the


A project was awarded based on a competitive proposal. Management made a commitment that a few key team members would be made posted on the project. When such assignments happen, they are termed as:

A. Bargaining agreements B. Schedule constraints C. Assignment risk D. Pre-assignments