Question: All EXCEPT drives tailoring: a. The guiding project management principles b. Organizational values and culture c. The project's budget and timeframe d. The type, size,

All EXCEPT drives tailoring:

a. The guiding project management principles

b. Organizational values and culture

c. The project's budget and timeframe

d. The type, size, and complexity of the project