Question: All the following are processes in project procurement management EXCEPT a. Terminate procurements b. Control procurements c. Plan procurement management d. Close procurements

All the following are processes in project procurement management EXCEPT—

a. Terminate procurements

b. Control procurements

c. Plan procurement management

d. Close procurements