Question: As project manager, you are about to start the scope definition process. You have the project charter, the organizational process assets list, and the project

As project manager, you are about to start the scope definition process. You have the project charter, the organizational process assets list, and the project scope management plan. Since there are no change requests in your project at this point, what must you have before you begin? A. Product analysis B. Preliminary project scope statement C. Updates to project scope management plan D. WBS