Question: Barbara is managing an educational program design project. The project is in a very early phase of the project lifecycle. This is a multi-million dollar


Barbara is managing an educational program design project. The project is in a very early phase of the project lifecycle. This is a multi-million dollar project and active involvement of the project key stakeholders is critical for the success of the project. Barbara has formed a board of project stakeholders so that all the key stakeholders can be kept engaged. Most of the key stakeholders have been conflicting with each other in the recent past. Most of the times, the nature of these conflicts have been personal rather than professional. However, no conflicts have yet arisen on the current project. Which of the following management skills must be applied by Barbara during the initial board meetings?

A. Change management B. Active listening C. Conflict resolution D. Trust building

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related PMP® Exam Practice Test And Study Guide Questions!