Question: Because risk management is relatively new on projects in your company, you decide to examine and document the effectiveness of risk responses in dealing with

Because risk management is relatively new on projects in your company, you decide to examine and document the effectiveness of risk responses in dealing with identified risks and their root causes. You therefore—

a. Conduct a risk audit

b. Hold a risk status meeting

c. Ensure that risk is an agenda item at regularly scheduled staff meetings

d. Reassess identified risks on a periodic basis