Question: Change control procedures, configuration management knowledge base, versions, and baselines in the develop project management plan process are: a. Enterprise environmental factors b. Organizational process
Change control procedures, configuration management knowledge base, versions, and baselines in the develop project management plan process are:
a. Enterprise environmental factors
b. Organizational process assets
c. Part of the project’s configuration management plan, which as a subsidiary plan will be part of the project management plan
d. Part of the organization’s management practices