Question: During project executing, a major problem occurs that was not included in the risk register. What should you do FIRST? A. Create a workaround. B.
During project executing, a major problem occurs that was not included in the risk register. What should you do FIRST? A. Create a workaround. B. Reevaluate the Identify Risks process. C. Look for any unexpected effects of the problem. D. Tell management.