Question: During the risk analysis process, you find that a specific risk has a remote chance of happening and if it occurs, it will have very
During the risk analysis process, you find that a specific risk has a remote chance of happening and if it occurs, it will have very little effect on the project objective. What will you do with this risk?
(a) Analyze it further
(b) Assign it a risk owner
(c) Keep it in watch list
(d) You will ignore it