Question: I I . A project manager must publish a project scheduh.. Activities, start/end times, and resources are identified. .Vhat should the project manager do next?

I I . A project manager must publish a project scheduh.•. Activities, start/end times, and resources are identified. \.Vhat should the project manager do next?

A. Distribute the project schedule according to the communications management plan.

B. Confirm the availability of the resources.

C. Refine the project management pl.in to reflect more accurate costing information.

D. Publish a bar chart illustrating the timeline.