Question: In project planning, the Work Breakdown Structure (WBS) is used to: a) Allocate tasks to team members b) Document project risks c) Decompose the project
In project planning, the Work Breakdown Structure (WBS) is used to:
a) Allocate tasks to team members
b) Document project risks
c) Decompose the project scope into manageable tasks
d) Track project expenses