Question: Midway through a project, a project manager determined that the project was running way behind schedule. If the project manager needs to shorten the project


Midway through a project, a project manager determined that the project was running way behind schedule. If the project manager needs to shorten the project schedule, without changing the project scope, which of the following schedule compression techniques could be applied?

A. Crashing B. Reserve Analysis C. Forecasting D. Last Tracking