Question: On your project to construct a new runway for your Citys airport, you are in the process of selecting vendors for various parts of this

On your project to construct a new runway for your City’s airport, you are in the process of selecting vendors for various parts of this project. You have conducted your make-or-buy analysis and have issued Requests for Proposals. You believe it is important to examine past performance of potential vendors. This means you are using—

a. Proposal evaluation techniques

b. Multi-disciplinary review teams

c. Analytical techniques

d. Independent estimates